As part of the World Bank's NELACEP project integrating the construction of the National Control Center and the Niamey's central control office, the first project was financed with funds made available to AFD and the second by the World Bank. The study which was done for AFD and Nigelec aimed to provide complementary and additional elements concerning the studies for the National Control Center and for the implementation of its financing. The study provided AFD and Nigelec with all the elements necessary for the design and sizing of the project, as well as the assessment of the feasibility of the investment. The study took into account the following elements: - SCADA / EMS; - The equipment of the substations; - The telecommunication and protection equipment; - The adaptation works in the substations; - The buildings accommodate the equipment.